If the pile reaches the required jacking load (termination criterion) but is significantly shorter than the design depth, the designer must evaluate whether the pile can be terminated early or if additional measures are required. 5. Eurocode 7 Compliance
The pile is typically jacked in incremental steps until the force reaches 2 to 2.5 times the Working Load (WL) Practical Refusal:
, focusing on safety, efficiency, and environmental benefits such as being vibration-free and low-noise Course Hero Key Installation & Termination Guidelines If the pile reaches the required jacking load
: For large-scale tests (exceeding 3000 tonnes), GeoSS recommends alternatives to traditional concrete block kentledge, such as steel plates tension piles bi-directional load tests , due to the risk of collapse.
: Use jacking machines up to 75% of their maximum rated capacity. Currently, machines in Singapore can handle capacities up to 800 tonnes for piles like 600mm diameter spun piles. Working Platform : Use jacking machines up to 75% of
The publication "Good Practice for Installation of Jacked Foundation Piles in Singapore," commonly referred to as the GEOSS Guide, stands as a seminal document in the local geotechnical engineering landscape. Developed by the Geotechnical Engineering Society of Singapore (GEOSS), this guide fills a critical void in the industry. For decades, jacked piles (also known as jacked-in piles or static pressed piles) were governed by fragmented specifications or经验主义 (empirical rules) passed down through contractors. This guide formalizes the methodology, offering a robust framework for the design, installation, and quality assurance of pre-formed piles installed via static jacking.
For full technical details, you can reference the Guideline on Jacked Piles Draft (GeoSS) or related Geotechnical Capacity documents . directional sequence (e.g.
For direct inquiries regarding GEOSS good practices and certification, contact: .
: Designers must account for highly variable geology, such as the Jurong Formation , where limestone cavities or undulating rock heads require probe holes at every pile location to ensure successful installation.
Once the target force is achieved and the pile reaches the desired depth, the Pjcap P sub j
In certain cases, a systematic, directional sequence (e.g., left to right) is adopted to ensure uniform soil displacement across the site. 4. Termination Criteria